Onshore

2005

1. Completed Cargo Valve Control system Partial Commissioning and Witness flushing at main deck/pump room of FPSO.

2005 to 2009

2. Completed WellHead Control Panel (WHCP) Installation, Flushing and Commissioning at Christmas Tree area of MOPU.

2006

3. Completed Cargo Valve Control system Commissioning and Witness flushing at main deck/pump room of FPSO.

2007-2008

4. Completed Cargo Valve Control system, Offloading Valve Commissioning and Witness flushing at main deck/pump room of FPSO.

2009

5. Completed Cargo Valve Control system Commissioning and Witness flushing at main deck/pump room of FPSO.

6. Completed Sub-sea HPU / Constant Tensioning Skid Installation, Flushing, Commissioning at Soft Yoke Mooring system of FPSO.

2010 to 2014

7. Completed Hydraulic Pressure Units Azimuth Thruster’s, Tubing Installation, Pressure Testing, Flushing, Maintenance /Service / Commissioning, Exchange / Repair underwater mountable thruster’s in pump room, pontoon on Drilling Rigs.

8. Completed Hydraulic Pressure Units Azimuth Thruster’s Testing/ Trouble Shooting/ Commissioning and Maintenance Live systems on Supply vessels.

2014

9. Completed Cargo Valve Control system, Offloading Valve Commissioning / Supervision flushing at main deck / pump room of FPSO.

10. Completed Project Manager Field Based for Cargo Valve Control systems, Manufacturing for FPSO.

11. Completed Cargo Valve Control systems, Manufacturing Onsite, Installation, FAT/SAT Subsea HPU, LCP’s, Pressure Testing, Flushing and Commissioning for FPSO.

2015

12. Completed Cargo Valve Control system, Offloading Valve, Riser Valves / HPU Commissioning/Modification, Supervision Flushing at main deck / pump room of FPSO.

2016

13. Completed Commissioning and Modification of Cargo Valve Control system, Offloading Valves, Riser valve balcony, System, Chemical skids, Partially Riser Tensioning system at main deck / pump room of FPSO.

14. Completed Survey on Cargo Valve Control system for FPSO.

2017

15. Completed Supervision Commissioning of Hydraulic Systems, Cargo Ballast Control System & Flushing at main deck/pump room at main deck / pump room of FPSO.

2018

16. Completed Supervision Pre-Commissioning of Flushing Hydraulic Systems at main deck / pump room of FPSO.

17. Completed Supervision Flushing / Commissioning of Cargo Valve Control system, Offloading Valves at main deck / pump room of FPSO.

18. Completed Commissioning Supervision of Cargo Valve Control system, HPU at workshop for FPSO.

19. Completed Hydraulic Modification Services at main deck / pump room of FPSO.

2019

20. Completed Supervision Commissioning / Services of Cargo Valve Control system at main deck / pump room of FPSO.

21. Completed Supervision & Team Retrofits / Modifications for Cargo Valve Control system, Cargo pumps and Hydraulics, Atex Inspection at main deck / pump room of FPSO.

22. Completed Turret Supervision at main deck / pump room of FPSO.

23. Completed Cargo Valve Control system Trouble shooting at main deck / pump room of FPSO.

2020

24. Completed Hydraulic Systems Survey at main deck / pump room of FPSO.

25. Completed complete vessel Multi systems Construction Supervisors (Electrical).

26. Completed Piping Flange Management on complete vessel.

2021

27. Completed Commissioning of Offloading system on poop deck.

2022

28. Completed Commissioning of Cargo Valve Control system, Farmo Cargo Ballast, Mooring Tensioning and Sub Sea HPU of complete FPSO vessel.

29. Carried out Survey on Cargo Valve Control system for FPSO.

30. Carried out Site Supervision Construction of 40 Well Control Skids at workshop.

31. Carried out Project Management of 3 x 5MW units.

32. Carried out Cargo Valve Control system, Hot Oil Flushing and SB Tubing Repair Services at main deck / pump room of FPSO.

33. Carried out Cargo Valve Control system / Valve Repairs Services at main deck / pump room / Tanks of FPSO.

34. Carried out Survey on Cargo Valve Control system, Chemical Skid and HPU at main deck / pump room of FPSO.

35. Carried out Survey / Maintenance on Cargo Valve Control system, Instrumentation Repair at main deck / pump room of FPSO.

2023

36. Carried out Survey and Services on Cargo Valve Control system at main deck / pump room of FPSO.

37. Carried out Survey on Chemical Skid at Turret on FPSO.

38. Carried out Cargo Valve Control system / Valves Services at main deck / pump room of FPSO.

39. Carried out Survey and Valve Repair Services at main deck / pump room of FPSO.

40. Carried out Chemical Skid Module Services / Commissioning.

41. Carried out Transformer Module Services.

42. Carried out Project Management for 3 x 5MW units.

43. Carried out Project Management for 1 x 1MW unit in Poland

44. Carried out Commissioning Supervision for 1 x 5MW unit in India.

45. Carried out Project Management for 9 x 1MW unit, 1 x 1MW unit and 3 x 1MW unit Testing in Vietnam.

46. Provide Commissioning Engineers for 3 x 1MW unit, 1 x 1MW unit and 9 x 1MW unit Testing in Vietnam